Monday, 29 July 2013

Week 3


29.7.2013 - Joy oh Joy the down side of building is coming home to a bill for $55,899.05. I guess that is the end of my $70 dollar mortgage payments. No more Ebay for me till Feb next year....Someone top up my paypal account for me



Monday, 22 July 2013

Week 2


22.7.2013 - My What a busy week, Piers done today. 8.7 Additional meters of peering required so just another Variation on the way. Met with James the slab supervisor who walked us around the site and explained the process from here. Expecting slab to be poured on Friday this week and frame due for delivery 1.8.2013. I love this part, looks like there will be visible changes every day this week. Yippee




Tuesday, 16 July 2013

Week 1


12.7.2013 - Received the call from out building supervisor to advise site was cut today and plumbers would be there 16.7 to commence work. peering is booked for 22.7. MMM will have to follow up now for the anticipated finish date, 20 weeks will be 29th of November and 26 weeks will be 10th of January.......Taking bets on finished before or after the christmas break.